The statement that does not refer to the reason that aids in project crashing is
(D) there are no critical activities that can be crashed further.
Explanation:
Project crashing basically refers to the method by which the duration of the project is reduced .This can be done by
In Crashing, the time is inversely related to the cost of the project.It means that if the time of the project increase then the project cost is reduced and if the time o/duration of the project decrease then the cost involved in the project increases